Please see below details as requested of each project.
Details Supplied
|
Current status of project
|
Dail Ref
|
40481/23 Bagenalstown, County Carlow in May 2015
|
24 new social homes completed Q3 2017 at a cost of €3.3m. Opened by Minister Eoghan Murphy in August 2017.
|
538
|
40482/23 Tullow, County Carlow in May 2015
|
16 new social homes completed Q4 2018 at a cost of €2m. Not opened by a Minister.
|
539
|
40483/23, Rathvilly, County Carlow in May 2015
|
10 new social homes completed Q2 2017 at a cost of €1.5m. Opened by Minister Damien English in May 2017.
|
540
|
40484/23 Myhill and Mount Leinster, County Carlow in May 2015
|
Myshall - 4 new social homes completed Q1 2018 at a cost of €641,935. Not opened by a Minister. Mount Leinster - 4 new social homes completed Q4 2017 at a cost of €550,027. Not opened by a Minister.
|
541
|
40485/23 Bagenalstown, County Carlow in July 2015
|
24 new social homes completed Q3 2017 at a cost was €3.3m. Opened by Minister Eoghan Murphy in August 2017.
|
542
|
40486/23 Borris, County Carlow in May 2015
|
4 new social homes completed Q3 2017 at a cost of €507,244. Not opened by a Minister.
|
543
|
40487/23 Rathvilly and Tullow, County Carlow in May 2015
|
1 new social home completed Q3 2017 at a cost of €140,000. Not opened by a Minister.
|
544
|
40488/23 Hacketstown, County Carlow in January 2016
|
4 new social homes completed Q4 2018 at a cost of €741,298. Not opened by a Minister.
|
545
|
40489/23 Vicar Street, County Kilkenny in May 2015
|
This 30 unit project as originally approved did not progress due to flooding concerns on the site.
|
546
|
40490/23 Bolton, Callan, County Kilkenny in May 2015
|
38 new social homes completed Q3 2020 at a cost of €7.1m. Not opened by a Minister.
|
547
|
40491/23 The Butts, County Kilkenny in May 2015
|
The appropriate re-zoning of this site was not achieved which meant the original social housing project could not advance. The council is looking at options for further development of new housing in this area.
|
548
|
40492/23 Donaguile, Castlecomer, County Kilkenny in May 2015
|
33 new social homes completed Q2 2021 at a cost of €8.37m. I opened this project in September 2021
|
549
|
40493/23 Robertshill, County Kilkenny in May 2015
|
The advancement of housing at this site has not been possible due to secondary flooding issues.
|
550
|
40494/23 Prologue/Westcourt/Moate, Callan, County Kilkenny in July 2015
|
The AHB originally planned to develop 16 new special needs social homes at dispersed locations, however they were unable to advance the project at that scale and ultimately delivered 1 new social home at Garden Cottage, Callan completed in Q4 of 2017 at a cost of €0.13m. Not opened by a Minister.
|
551
|
40495/23 Greenshill, County Kilkenny in July 2015
|
This project did not proceed as the AHB was unable to complete the purchase of the site
|
552
|
40496/23 Ballytobin, Callan, County Kilkenny in July 2015
|
This project was withdrawn as the AHB involved was unable to advance it.
|
553
|
40497/23 Leamy Street, Waterford in July 2015
|
This project was delivered under the Repair and Leasing scheme completed in Q4 2018 at a cost of €400,000. Not opened by a Minister.
|
554
|
40498/23 Gleann Ealach, Dunhill, Waterford in July 2015
|
This project was withdrawn due to a refusal of planning permission.
|
555
|
40499/23 Powers Field, Hennessy's Road, Waterford in January 2016
|
The original project could not be advanced on a viable basis by the AHB and options for new social housing delivery on this site are being explored by WCCC.
|
556
|
40500/23 Wadding Manor, Ferrybank, Waterford in January 2016
|
10 new social homes completed Q2 2021 at a cost of €2.1 million. Not opened by a Minister.
|
557
|
40501/23 An Garran, Tramore, Waterford in January 2016
|
This 50 unit project project is currently on-site and scheduled for completion in Q4 2024. The current approved budget is €18.1 million.
|
558
|
40502/23 Ardmore Park - Priory Lawn, Waterford in May 2015
|
8 new social homes completed Q3 2020 at a cost of €1 million. Not opened by a Minister
|
559
|
40503/23 Ballinroad, Dungarvan, Waterford in May 2015
|
21 new social homes completed Q2 2020 at a cost of €4.6 million. Not opened by a Minister
|
560
|
40504/23 Coolfin Woods, Portlaw, Waterford in May 2015
|
12 new social homes completed Q2 2019 at a cost of €2.4 million. Not opened by a Minister
|
561
|
40505/23 Larchville, Waterford in May 2015
|
5 new social homes completed Q2 2021 at a cost of €1.4 million. Not opened by a Minister
|
562
|
40506/23 Tallow Alms House, Waterford in May 2015
|
4 new social homes completed Q4 2018 at a cost of €666,593. Not opened by a Minister
|
563
|
40507/23 Barrack St, Cappoquin, Waterford in May 2015
|
4 new social homes completed Q4 2017 at a cost of €875,633. Not opened by a Minister
|
564
|
40508/23 Patrick St., Waterford in May 2015
|
2 new social homes completed Q3 2018 at a cost of €562,192. Not opened by a Minister
|
565
|
40509/23 Cathal Brugha, Dungarvan, Waterford in May 2015
|
The project as proposed did not proceed and instead improvement works to the properties concerned were carried out under Retrofit Programmes.
|
566
|
40510/23 Kells, County Meath in May 2015
|
40 new social homes completed Q4 2020 at a cost of €9.98 million. I opened the project in April 2022.
|
567
|
40511/23 Athboy, County Meath in May 2015
|
32 new social homes completed Q2 2018 at a cost of €8.5 million. Opened by Minister Damien English in August 2018.
|
568
|
40512/23 Summerhill, County Meath in May 2015
|
19 new social homes completed Q4 2020 at a cost of €4.3 million. Not opened by a Minister.
|
569
|
40513/23 Kilbride Lane, Bray, County Wicklow in July 2015
|
42 new social homes completed, Phase 1 (23 homes) completed Q4 2020 and Phase 2 (19 homes) completed Q2 2021 at a cost of €17.34m. Not opened by a Minister
|
570
|
40514/23 Dunlavin (Phase 1), County Wicklow in May 2015
|
The project did not proceed due to flooding risks at the site
|
571
|
40515/23 Brewery Bends (Phase 2), Rathdrum, County Wicklow in May 2015
|
20 new social homes completed Q4 of 2018 at a cost of €4.57m. Opened by Minister Andrew Doyle in December 2018
|
572
|
40516/23 Kilnagleary, Carrigaline, County Cork in May 2015
|
49 new social homes completed, Phase 1 (10 units) and Phase 2 (5 Units) in Q4 2018, Phase 3 (16 Units) Q1 2019 and Phase 4 (18 Units) Q1 2019 at a cost of €12.5m. Not opened by a Minister.
|
573
|
40517/23 Beechgrove, Clonakilty, County Cork in May 2015
|
57 new social homes completed, Phase 1 (51 units) Q4 2021 and Phase 2 (6 units) Q2 2022 at a cost of €18.3m. Not opened by a Minister.
|
574
|
40518/23 Rosscarbery, County Cork in July 2015
|
9 new social homes completed Q1 2019 at a cost of €2.3m. Not opened by a Minister.
|
575
|
40522/23 Mount St. Joseph, Chapel Hill, Macroom, County Cork in July 2015
|
The project was withdrawn by the AHB as it was not economically viable. The needs to be supported by this project will be met through an alternative project, which is at pre-tender stage.
|
579
|
40523/23 Castletreasure, Donnybrook, Douglas, County Cork in January 2016
|
12 new social homes completed Q1 2017 at a cost of €2.8m. Opened by Minister Simon Coveney.
|
580
|
40524/23 Midleton, County Cork in January 2016
|
This project received approval as a Turnkey in 2016 but was subsequently withdrawn by the developer. The project was resubmitted as a 70 unit SHIP Construction project was approved in 2018. However, the project was put on hold in 2021 due to issues with NAMA and Irish Water.
|
581
|
40525/23 Passage West, County Cork in January 2016
|
This project was withdrawn by the Council due to An Bord Pleanala overturning the Council’s decision to grant permission for the development.
|
582
|
40526/23 Ballincollig, County Cork in January 2016
|
The project was withdrawn by the Council on 20 July 2017.
|
583
|
40527/23 Mitchels Road, Tralee, County Kerry in July 2015
|
18 new social homes are on site and due to complete shortly at an estimated cost of €4.7m.
|
584
|
40528/23 The Park, Killarney, County Kerry in May 2015
|
12 new social homes completed Q2 2018 at a cost of €2.1m. Opened by Minister Eoghan Murphy in July 2018.
|
585
|
40529/23 Killeen, County Kerry in May 2015
|
12 new social homes completed Q3 2019 at a cost of €2.2m. Not opened by a Minister.
|
586
|
40530/23 County Kerry in May 2015
|
9 new social homes completed between 2018 and 2022. Not opened by a Minister. 1 new social home currently onsite and due for completion Q2 2024. 2 other social homes are delayed due to legal issues.
|
587
|
40531/23 Lixnaw, County Kerry in May 2015
|
4 new social homes completed in Q4 2017 at a cost of €650,000. Not opened by a Minister.
|
588
|
40532/23 The Park, Killarney, County Kerry in January 2016
|
8 new social homes completed in Q2 2018 at a cost of €1.4m. Opened by Minister Eoghan Murphy in July 2018.
|
589
|
40533/23 Killeen, County Kerry in January 2016
|
9 new social homes completed in Q3 2019 at a cost of €1.6m. Not opened by a Minister.
|
590
|
40534/23 Listowel, County Kerry in January 2016
|
7 new social homes completed in Q4 2019 at a cost of €1.7m. Not opened by a Minister.
|
591
|
40535/23 Milltown, Bridewell, County Kerry in January 2016
|
8 new social homes completed in Q4 2019 at a cost of €2m. Not opened by a Minister.
|
592
|
40536/23 Bill Kinnerk Road, Tralee, County Kerry in January 2016
|
4 new social homes completed in Q1 2018 at a cost of €4.2m. Not opened by a Minister.
|
593
|
40537/23 Kenmare, County Kerry in January 2016
|
22 new social homes completed in Q4 2018 at a cost of €4.3m. Opened by Minister Eoghan Murphy in July 2019.
|
594
|
40538/23 Tubberhill, Westport, County Mayo in May 2015
|
21 new social homes (increased from 20) completed in Q1 2018 at a cost of €5.6m. Not opened by a Minister.
|
595
|
40539/23 County Mayo in July 2015
|
5 new social homes completed Q2 2017 and Q2 2018 at a cost of €1.1m. Not opened by a Minister.
|
596
|
40540/23 Knockferreen, Kilmaine Road, Ballinrobe, County Mayo in July 2015
|
6 new social homes completed in Q4 2018 at a cost of €0.9m. Not opened by a Minister.
|
597
|
40541/23 Marian Cresent, Ballina, County Mayo in May 2015
|
4 new social homes (increased from 3) completed in Q2 2018 at a cost of €0.8m. Opened by Minister Damian English in May 2018.
|
598
|
40542/23 Knockmore, Ballina, County Mayo in January 2016
|
8 new social homes completed in Q1 2019 at a cost of €2m. Opened by Minister Eoghan Murphy in March 2019.
|
599
|